Multi-shift operation in practice
M12 studs with lengths of 30, 60 and 70 mm are welded. The components are subjected to high mechanical loads in their subsequent application. Production runs in multiple shifts with a high cycle rate.

This application example shows fully automatic drawn arc stud welding under shielding gas on primer-coated Hardox 450.
M12 studs with lengths of 30, 60 and 70 mm are welded. The components are subjected to high mechanical loads in their subsequent application. Production runs in multiple shifts with a high cycle rate.
X, Y and Z dimensions and process equipment are matched to the material, component and production task. The key technical data below describe the configuration of this example system.
An insight into the production process on the CNC system.
The welding heads and application in operation.
Tell us about the machine specifications, required equipment, welding heads and accessories. We will clarify any incomplete details together.